Planning Applications Reference:12/01613/REG03

Further Information on this property is available on the Council's My House web page.

View Further Information
Type of Application:Regulation 3 Application
Status:Pending Consideration
Address of Proposal:Victoria Bridge, Victoria Bridge Road, Kingsmead, Bath, Bath And North East Somerset, BA1 3AY
Ward:Kingsmead
Proposal:Emergency works to install a temporary Mabey girder above the existing bridge deck for the purpose of: a.Providing an independant system of support to the existing bridge deck to prevent collapse in the event of failure. b. Allowing temporary pedestrian access across the River for members of the public. c. Providing safe means of access to facilitate a third phase of work, which will enable the route across the River at Victoria Bridge to be reopened to the public on a permenant basis. d. Investigation works to the Bridge's foundations to inform design of the above future works (Retrospective)
Applicant Name:Bath & North East Somerset Council
Agent Name:Buro Happold
Agent Address:Camden Mill, Lower Bristol Road, Bath, BA2 3DQ
Case Officer Name:Martin Almond
Date Application Received:10/04/2012
Date Application Validated:25/04/2012
Standard Consultations sent on:26/04/2012
Last advertised on:03/05/2012
Latest Site Notice posted on:07/05/2012
Expiry Date for Consultation :28/05/2012
Target Decision Date20/06/2012

Documents

ConstraintsAgric Land Class 3b,4,5, Article 4, Conservation Area, Flood Zone 2, Flood Zone 3, Forest of Avon, Hotspring Protection, Listed Building, Sites of Nature Conservation Interest, Sites with Planning Permission, World Heritage Site
Related Property:Victoria Bridge,Victoria Bridge Road,Kingsmead,Bath,BA1 3AY.
Reference Proposal Application Received Status
12/01614/REG13 .Emergency works to install a temporary Mabey girder above the existing bridge deck for the purpose of: a.Providing an independant system of support to the existing bridge deck to prevent collapse in the event of failure. b. Allowing temporary pedestrian access across the River for members of the public. c. Providing safe means of access to facilitate a third phase of work, which will enable the route across the River at Victoria Bridge to be reopened to the public on a permanant basis. d. Investigation works to the Bridge's foundations to inform design of the above future works (Regularisation)10/04/2012Pending Consideration
12/01613/REG03 .Emergency works to install a temporary Mabey girder above the existing bridge deck for the purpose of: a.Providing an independant system of support to the existing bridge deck to prevent collapse in the event of failure. b. Allowing temporary pedestrian access across the River for members of the public. c. Providing safe means of access to facilitate a third phase of work, which will enable the route across the River at Victoria Bridge to be reopened to the public on a permenant basis. d. Investigation works to the Bridge's foundations to inform design of the above future works (Retrospective)10/04/2012Pending Consideration
13/01905/REG13 .Deconstruction of Victoria Bridge and reconstruction using existing components where feasible and incorporating new materials where necessary to make the bridge safe for public use and surfacing works to the bridge approaches.03/05/2013Consent
13/04918/LBA .External work which includes lighting proposal for bridge that is being refurbished.11/11/2013Consent
13/05063/COND .Discharge of conditions 1-12 to Planning Application 13/01905/REG13 (Deconstruction of Victoria Bridge and reconstruction using existing components where feasible and incorporating new materials where necessary to make the bridgesafe for public use). The proposals include surfacing works to the bridge appraoches.20/11/2013Condition Discharged

The Comments tab lists all public comments received on this application (not statutory consultees, e.g. The Environment Agency, Highways DC, etc). The majority of comments are submitted via our Comments Form through the website and you can expand the comment to view all of the text by clicking on the plus button. A minority of comments are submitted by post or email and it is not possible to include all the text here, however when you expand the comment you will see a link to our Associated Documents page where you can search for the comment.


Name Address Comment type Comment1 Comment2 Comment3 Date